Claim No. CFI 020/2013
THE DUBAI INTERNATIONAL FINANCIAL CENTRE
COURTS
Court
IN THE
COURT
OF FIRST INSTANCECourt
BEFORE JUSTICE SIR JOHN CHADWICK
BETWEEN
SARINTON TRADING INC |
Claimant
Claimant
|
and MR ANDREAS MICHAEL REICHMUTH |
Defendant
Defendant
|
DEFAULT JUDGMENT
UPONthe Application by the Claimant dated 14 November 2013.
UPONreading (1) the Claim Form and Particulars of Claim; (2) the Request for Default Judgment dated 14 November 2013; and (3) the First Affidavit
Affidavit
UPONhearing Counsel for the Claimant on 17 December 2013.
AND UPONthe Court
Court
IT IS DECLARED THAT:
Subject to the consent of Damac Real Estate Asset Management Company Limited, the interests of the Defendant under the Sale and Purchase Agreements dated 13 May 2007 for unit numbers DFA/29/A2905, DFA/29/A2906, DFO/P7A/7 and DFO/P7A/8 in Park Towers at the Dubai International Financial Centre have been wholly assigned to the Claimant.
AND IT IS ORDERED THAT:
1 The costs of and associated with the Claimant's claim and the Claimant's application for default judgment will be subject to a detailed assessment before the
DIFC Courts
Registrar
.
DIFC Courts
Registrar
2 The Claimant shall be at liberty to apply to the Court for:
(a) damages resulting from the Defendant's breach of the Assignment Agreement;
(b) pre- and post-judgment interest on any damages, costs or disbursements; and
(c) such further or other relief as the Court may deem just.
Dated 17 December 2013.
Pursuant toDIFC
Set aside