Claim No. SCT 317/2020 THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS
Claim No. SCT 317/2020
THE DUBAI INTERNATIONAL FINANCIAL CENTRE
COURTS
In the name of His Highness Sheikh Mohammed Bin Rashid Al Maktoum,
Ruler
IN THE SMALL CLAIMS
TRIBUNAL
BEFORE SCT
JUDGE
BETWEEN
LISANA FZ LLE
Claimant
and
LUKNA ADVERTISING LLC
Defendant
Hearing : | 20 October 2020 |
---|---|
Judgment : | 8 November 2020 |
JUDGMENT OF SCT JUDGE MAHA AL MEHAIRI
UPONthe Claim Form being filed on 30 August 2020
AND UPONthe Defendant filing
AND UPONa Hearing having been held before SCT Judge
AND UPONreading the submissions and evidence filed and recorded on the Court
IT IS HEREBY ORDERED THAT:
1. The Defendant shall pay the Claimant the sum of AED 8,000.
2. The Defendant shall pay the Claimant the Court fee in the sum of AED 367.25.
Issued by:
Ayesha Bin Kalban
SCT Judge and
Deputy Registrar
Date of issue: 8 November 2020
At: 2pm
THE REASONS
The Parties
1. The Claimant is Lisana (“the “Claimant”), a company registered in Fujairah, UAE
2. The Defendant is Lukna Advertising LLC (the “Defendant”) a company registered in Dubai, UAE.
Background and the Preceding History
3. The underlying dispute arises over an agreement with regard to the provision of public relations for the Defendant carried out by the Claimant pursuant to an agreed and signed Public Relations Agreement (the “Agreement”), and the Defendant’s failure to pay the Claimant the sums due pursuant to the Agreement.
4. On 13 September 2020, the Claimant filed a claim in the DIFC Courts
5. On 17 September 2020, the Defendant filed an Acknowledgment of Service
6. The parties met for a Consultation before SCT Judge Hayley Norton on 27 September 2020 but the parties failed to settle the Claim.
7. In line with the rules
The Claim
8. The Claimant’s case is that the parties entered into an Agreement in November 2019 with a commencement date on 3 November 2019. The Agreement consisted of a retainer fee of AED 8,000 per month paid by the Defendant to the Claimant, and the payment plan agreed by the parties was for the payment of AED 4,000 to be made at the beginning of the month and the remainder amount AED 4,000 to be settled at the end of each month.
9. The Claimant submits that it has conducted work for the period of two months (end of February and beginning of March) without receiving payment. However, in relation to the month of February, the Defendant refused to pay the Claimant, stating that it had already paid all payments due to the Claimant on time and has provided evidence of receipts paid by the Defendant to the Claimant during the mentioned contract period.
10. The Claimant also alleges that during those dates, it completed a full on 3-day influencer event, dispatched press releases and generated coverage for the Defendant’s brand.
11. The Claimant submits that the Defendant has disregarded the hard work the Claimant has put into the Defendant’s brand without paying what are due pursuant to the Agreement.
12. Therefore, the Claimant claims the payment of the retainer fee in the amount of AED 8,000 for pending invoices, as well as the amount AED 2,000 for damages it has incurred as a result of the Defendant’s failure to make payment to the Claimant, in addition to the court
The Defence
13. The Defendant alleges that the Claimant is not entitled to the claimed amount, and submits that the duration it takes to build a campaign is 2 to 3 weeks, so the Claimant did initiate work from the 3rd of November 2019, but the first work deliverable was only set out to be in December and so on.
14. The Defendant submits that it paid the Claimant the amount of AED 28,840 for the work that was done in November to February, and the total amount of the contract agreed is AED 25,200. The Defendant submits that the additional amount of AED 3,240 is for additional extra work that the Claimant had carried out on behalf of the Defendant. Therefore, the Defendant denies that the Claimant is entitled to seek any further amounts against it.
Discussion
15. The parties are both registered and located outside of the DIFC
“This contract shall be applicable under the rules and jurisdiction of the DIFC Courts (Dubai International Financial Centre). Any dispute arising out of or in connection with this contract, including any question regarding its existence, validity or termination, or failure to pay, shall be subject to the exclusive jurisdiction of the Courts
16. The Claimant argues that the Defendant at some point did acknowledge that it owed the Claimant amounts and then denied it by providing documents as a proof of payment for February and March.
17. The Defendant insists that it has paid all payments due and has supported that submission by sending receipts as proof via email. The Claimant submitted evidence that the Defendant never contested owing them the amounts in emails and WhatsApp conversations. Reports showcasing results and emails showcasing work between parties during the months owed were also provided.
18. The Court is satisfied that the Claimant has provided sufficient evidence to support its Claim. The Defendant did not raise any issues with the quality of work or issues with the invoices sent until the Claimant filed a Claim with the Courts. The parties agreed on a mechanism for payment in the Agreement which reads:
“5. Payments
a. The Client agrees to pay the Firm a 50% advance payment prior to the start of each cycle (month).and 50% at the end of each month. Each end of month payment will be made along with the beginning of the following month.”
19. This mechanism for payment contradicts the Defendant’s understanding being that it should pay the Claimant ahead of each project. The Defendant is in breach of its obligations with respect to the Agreement. The Claimant to receive payment for the events performed and work completed in the duration mentioned being the last 2 weeks in February and first 2 weeks of March.
Costs
20. At the Hearing, the Claimant pled for its costs, arguing that the matter wasted the Claimant’s time and efforts when she could have worked on other projects instead of pursuing the claim. The general rules regarding costs in the SCT reads:
“Costs in the SCT
53.70
The SCT may not order a party to a small claim to pay a sum to another party in respect of that other party’s costs, fees and expenses, including those relating to an appeal, except:
(1) such part of any Court or Tribunal fees paid by that other party as the SCT may consider appropriate;
(2) such further costs as the SCT may assess by the summary procedure and order to be paid by a party who has behaved unreasonably.”
21. In this matter, I cannot find that the Defendant has behaved “unreasonably” such to make it appropriate to grant the Claimant its costs in the SCT. The Defendant did not act in a way to prolong the matter or unjustifiably increase the costs related to the matter. The Claimant has not pointed to any other behaviour, other than its potential success of the Claim and that it had to go through the process of filing a claim for an amount that is not disputed, to justify granting costs in this matter. Thus, I cannot grant the Claimant’s request for costs in the matter and the parties shall bear their own costs.
Conclusion
22. In light of the aforementioned, I find that the Defendant shall pay the Claimant the total sum of AED 8,000.
23. The Defendant shall pay the Claimant the court fee in the sum of 367.25.
Issued by:
Ayesha Bin Kalban
SCT Judge and Deputy Registrar
Date of issue: 8 November 2020
At: 2pm